Thursday, November 20, 2025

PROJECT FINANCE Q&A FOR RICS APC INTERVIEW

 

SECTION 1 — INTRODUCTION TO PROJECT FINANCE

  1. Q: What is project finance?
    A: Financing based on a project’s future cashflows, using a ring-fenced SPV.

  2. Q: Why do large infrastructure projects use project finance?
    A: It allocates risk to parties best placed to manage it and enables off-balance sheet funding.

  3. Q: What is an SPV?
    A: A Special Purpose Vehicle set up to develop, finance, own, and operate a project.

  4. Q: Key characteristic of project finance?
    A: Non-recourse or limited-recourse debt.

  5. Q: What assets do lenders rely on?
    A: Project cashflows and project contracts, not shareholder balance sheets.

  6. Q: What is non-recourse financing?
    A: Lenders can only claim against the project assets, not the sponsor’s assets.

  7. Q: What is limited-recourse financing?
    A: Lenders have some fallback rights to sponsors under defined conditions.

  8. Q: What is a concession?
    A: Long-term right to build/operate an asset granted by a government authority.

  9. Q: What is “bankability”?
    A: The likelihood that lenders will provide financing.

  10. Q: Why form an SPV instead of using a parent company?
    A: To isolate risk and simplify contractual relationships.


SECTION 2 — PPP / PFI / CONCESSIONAL MODELS

  1. Q: What is PPP?
    A: Public Private Partnership—collaboration between public and private sectors to deliver assets/services.

  2. Q: What is PFI?
    A: Private Finance Initiative—private sector finances, builds, and operates public infrastructure.

  3. Q: Common PPP models?
    A: Build-Operate-Transfer (BOT), BOOT, DBFO, Concession, O&M contracts.

  4. Q: Example DBFO meaning?
    A: Design, Build, Finance & Operate.

  5. Q: What drives value for money in PPP?
    A: Optimal risk transfer, lifecycle efficiencies, whole-life cost focus.

  6. Q: What is a shadow toll?
    A: Government pays operator based on traffic volumes rather than end-users paying.

  7. Q: Why are PPPs attractive to governments?
    A: Capex doesn’t hit public accounts immediately; risk transferred to private sector.

  8. Q: Typical PPP concession length?
    A: 20–40 years depending on asset class.

  9. Q: What is availability-based payment?
    A: Government pays operator based on asset availability & performance, not usage.

  10. Q: Why do PPP projects face criticism?
    A: Long-term cost to public sector; contract inflexibility.


SECTION 3 — FUNDING STRUCTURES

  1. Q: What is equity in project finance?
    A: Capital contributed by sponsors at risk of loss.

  2. Q: What is senior debt?
    A: First to be repaid; lowest risk, lowest interest rate.

  3. Q: What is subordinated debt?
    A: Higher-risk debt repaid after senior lenders.

  4. Q: What is mezzanine financing?
    A: Hybrid debt with equity-like features, higher return.

  5. Q: Typical debt-to-equity ratio in PF?
    A: 70:30 to 90:10 depending on project stability.

  6. Q: Advantages of high leverage?
    A: Lower sponsor equity requirement; higher IRR.

  7. Q: Disadvantages of high leverage?
    A: Higher repayment burden; increased default risk.

  8. Q: What is the cost of capital?
    A: Weighted average cost of debt and equity (WACC).

  9. Q: What is refinancing?
    A: Replacing debt with cheaper debt once project risk reduces.

  10. Q: Why do lenders require technical due diligence?
    A: To confirm feasibility, cost accuracy, and programme risk.


SECTION 4 — FINANCIAL MODELLING (NPV / IRR / CASHFLOW)

  1. Q: What is NPV?
    A: Net Present Value — discounted value of future cashflows.

  2. Q: What is a positive NPV?
    A: Indicates a financially viable project.

  3. Q: What is IRR?
    A: Internal Rate of Return — discount rate that makes NPV = 0.

  4. Q: What is the payback period?
    A: Time required for cash inflows to recover initial investment.

  5. Q: What is discounted cash flow (DCF)?
    A: Method of valuing based on time value of money.

  6. Q: Difference between nominal and real cashflows?
    A: Nominal includes inflation; real excludes it.

  7. Q: What is a financial close?
    A: Point when project contracts & funding agreements are signed.

  8. Q: What is a debt service coverage ratio (DSCR)?
    A: Cashflow available for debt service ÷ debt service obligations.

  9. Q: Typical required DSCR?
    A: 1.2–1.5 depending on project risk.

  10. Q: What is a lock-up covenant?
    A: Restriction preventing dividend payments when DSCR too low.


SECTION 5 — COSTING, BUDGETING & FORECASTING

  1. Q: Role of QS in project finance?
    A: Cost verification, lifecycle costing, CAPEX/OPEX modelling, value engineering.

  2. Q: What is CAPEX?
    A: Capital expenditure for constructing the asset.

  3. Q: What is OPEX?
    A: Operational expenditure during asset life.

  4. Q: What is lifecycle cost?
    A: Total cost of ownership including maintenance and operations.

  5. Q: Why is cost accuracy critical at financial close?
    A: Lenders rely on fixed price or near-fixed price CAPEX.

  6. Q: What is a base cost estimate?
    A: Construction cost before risk, inflation, and financing.

  7. Q: What is owner's contingency?
    A: Allowance for undefined risks retained by the sponsor.

  8. Q: What is lender’s technical advisor (LTA)?
    A: Independent expert who validates cost and schedule on behalf of lenders.

  9. Q: Why fixed-price contracts favoured in PF?
    A: They limit CAPEX risk and protect lenders.

  10. Q: What is a whole-life cost approach?
    A: Evaluating CAPEX + OPEX to optimise long-term value.


SECTION 6 — COMMERCIAL CONTRACTS IN PROJECT FINANCE

  1. Q: What is an EPC contract?
    A: Engineering, Procurement & Construction — lump-sum turnkey contract for construction.

  2. Q: Why is EPC preferred in PF?
    A: Single point of responsibility and fixed cost/time.

  3. Q: What is O&M contract?
    A: Contract for long-term operation and maintenance.

  4. Q: What is a long-term offtake agreement?
    A: Buyer commits to purchase output (e.g., power purchase agreement).

  5. Q: What is a supply agreement?
    A: Contract securing inputs (e.g., fuel, raw materials).

  6. Q: What is a tripartite agreement?
    A: Links lender, SPV, and contractor to protect lender interests.

  7. Q: What is a direct agreement?
    A: Gives lenders rights to step-in if SPV defaults.

  8. Q: What is force majeure?
    A: Unforeseeable events beyond control of parties.

  9. Q: What is a completion guarantee?
    A: Sponsor guarantee ensuring project completion.

  10. Q: What is risk sharing?
    A: Allocating risks to parties best able to mitigate them.


SECTION 7 — RISK ANALYSIS & MITIGATION

  1. Q: Key risks in project finance?
    A: Construction risk, cost overrun risk, demand risk, O&M risk, political risk.

  2. Q: What is construction risk?
    A: Risk that project may be delayed, over-budget or technically deficient.

  3. Q: How is construction risk mitigated?
    A: EPC contract, performance bonds, guarantees.

  4. Q: What is demand risk?
    A: Risk that the asset will not generate expected revenue.

  5. Q: How is demand risk mitigated?
    A: Offtake agreements, minimum revenue guarantees.

  6. Q: What is political risk?
    A: Government actions impacting project (e.g., expropriation).

  7. Q: What is inflation risk?
    A: Increase in costs or decrease in real value of payments.

  8. Q: How do lenders manage FX risk?
    A: Hedging, matching currency of debt with revenue.

  9. Q: What is termination risk?
    A: Risk of project ending early due to breach or political factors.

  10. Q: What is insurance used for in PF?
    A: Transfer financial impact of events (accidents, natural disasters).


SECTION 8 — PUBLIC SECTOR & ECONOMIC APPRAISAL

  1. Q: What is the public sector comparator (PSC)?
    A: Benchmark comparing PPP cost vs public delivery.

  2. Q: What is value for money (VfM)?
    A: Optimal balance of cost, quality, and risk transfer.

  3. Q: What is economic appraisal?
    A: Assessment using social and economic benefits (not just financial).

  4. Q: What is social cost-benefit analysis?
    A: Evaluating wider economic impacts of a project.

  5. Q: Example of economic multiplier effect?
    A: Jobs created leading to increased local spending.

  6. Q: What is optimism bias?
    A: Tendency to underestimate costs and overestimate benefits.

  7. Q: Why do governments use discount rates?
    A: To reflect opportunity cost of capital and compare future benefits.

  8. Q: What is the HM Treasury Green Book?
    A: UK guidance on project appraisal and evaluation.

  9. Q: What is affordability analysis?
    A: Whether future payments are within government budget.

  10. Q: Why perform sensitivity analysis?
    A: To test how results change with uncertainties in assumptions.


SECTION 9 — EQUITY, RETURNS & INVESTOR PERSPECTIVE

  1. Q: What returns do equity investors expect?
    A: Higher than lenders due to higher risk—typically IRR 10–20%.

  2. Q: What is equity IRR?
    A: Return to shareholders after debt servicing.

  3. Q: What is project IRR?
    A: Return on total project cashflow before financing.

  4. Q: What increases equity returns?
    A: Higher leverage, refinancing, CAPEX savings.

  5. Q: Why do investors monitor DSCR?
    A: Indicates ability to service debt; impacts dividend payments.

  6. Q: What is a waterfall structure?
    A: Order in which project revenues are distributed.

  7. Q: What is cash sweep?
    A: Using excess cash to repay debt early.

  8. Q: What is hurdle rate?
    A: Minimum acceptable return to investors.

  9. Q: Why do investors favour stable revenue assets?
    A: Lower risk, predictable returns.

  10. Q: What is exit value?
    A: Value realised when selling equity stake.


SECTION 10 — LENDERS, DUE DILIGENCE & FINANCIAL CLOSE

  1. Q: Why is lender due diligence extensive?
    A: To protect investment and ensure project viability.

  2. Q: What is a term sheet?
    A: Outline of loan terms prior to full loan agreement.

  3. Q: What is covenant testing?
    A: Monitoring compliance with loan conditions (e.g., DSCR).

  4. Q: What is a step-in right?
    A: Allowing lender to replace SPV operator if project underperforms.

  5. Q: When is final investment decision made?
    A: Once financial modelling, due diligence, contracts, and funding are confirmed.

  6. Q: What is lender’s monitor?
    A: Independent party overseeing construction for lenders.

  7. Q: What is drawdown schedule?
    A: Timing and amount of each loan disbursement.

  8. Q: What is completion test?
    A: Required performance and reliability thresholds before full operation.

  9. Q: What is a subordinated sponsor loan?
    A: Equity-like debt provided by sponsors, repaid after senior lenders.

  10. Q: What causes project finance deals to fail?
    A: Poor risk allocation, weak contracts, unviable cashflows, political instability.

No comments:

Post a Comment